Hope that helps…Larry, When I go to project center in PWA and the go to reports tab and open the report in question once it loads I have to edit it in excel to refresh the connections.

If that is the case then I am sure the refreshing of Odata external just compounds the issue.Darren, Power Query might be the issue here as it uses a different connection solution then normal Excel and can be problematic to a basic Share Point page.Try creating a simple Excel workbook with a basic data connection (no Power Query) and see if that successfully refreshes.* If the task is complete in PWA (in the schedule PDP in view mode or any other view) then the task update has been published.Viewing a schedule in PWA displays the published version, edit mode displays the working version.